Project Timeline
Following is an estimated timeline for anticipated project activities. The project timeline can be affected by activities that take place during each phase of work, and by funding, since each phase of the work may be funded separately.
Phase I
Phase I construction and landscaping is complete. |
CBRT Meetings |
||
|
December 2004 through Spring 2007 |
|
Public Workshop |
||
|
August 29, 2005 |
|
Public Hearing |
||
|
November 14, 2005 |
|
Environmental Public Meeting |
||
| January 25, 2007 | ||
CSS Close-out Meeting |
||
|
Spring 2007 |
|
Future Phase II Activities Anticipated
Environmental Assessment |
||
| Draft Document Complete late Summer 2012 Public Hearing Spring 2013 Final Document completed Summer 2013 |
||
Design |
||
| 12 to 18 months (currently not scheduled) | ||
Right-of-Way Phase |
||
|
18 to 24 months (currently not scheduled) |
|
Construction Phase |
||
|
24+ months (currently not scheduled) |
|