321 East Parkway (US 321, State Route 73)

Project Timeline


Following is an estimated timeline for anticipated project activities. The project timeline can be affected by activities that take place during each phase of work, and by funding, since each phase of the work may be funded separately.

Phase I

Phase I construction and landscaping is complete.

Phase II

CBRT Meetings

 

December 2004 through Spring 2007

 

Public Workshop

 

August 29, 2005

 

Public Hearing

 

November 14, 2005

 

Environmental Public Meeting

  January 25, 2007  

CSS Close-out Meeting

 

Spring 2007

 

Future Phase II Activities Anticipated

Environmental Assessment

  Environmental Studies for this project remain in progress. After completion, anticipated timelines for remaining development phases will be determined.  

Design

  12 to 18 months (currently not scheduled)  

Right-of-Way Phase

 

18 to 24 months (currently not scheduled)

 

Construction Phase

 

24+ months (currently not scheduled)