Project Timeline

  • Initial Milestone: Aerial and ground survey completed 01/10/2013.
  • Environmental Studies / Document: Spring 2014
  • Design Public Meeting: : Spring 2014; Details TBA
  • Final Right-of-Way Plans: Spring 2014*
  • Right-of-Way Acquisition: Spring 2015*
  • Let out for Construction Bids: Summer 2015*

* denotes estimated completion timeframe.