Project Timeline
Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way and Construction. The following is a reflection of various aspects of these phases as they have occurred or will occur on the improvement of S.R. 11 (Nolensville Road):
| Current Schedule |
| Initial Public Meeting |
Conducted January 9, 2006 |
| Advanced Planning Report |
Completed January 12, 2006 |
| Public Information Meeting |
Completed April 29, 2008 |
Future Milestones (this project is now listed in the TDOT Budget Program for Fiscal Year 2014 to begin Appraisals and Acquisitions) |
| Conduct Design Public Meeting |
Scheduled for Fall 2013 |
| Approval of Final Environmental Document |
Scheduled for Spring 2014 |
| Appraisals and acquisition of properties |
Scheduled for Spring 2014 |
 |
| The project is currently in the Environmental phase. An environmental document is being developed for review by Federal Highway Administration (FHWA), other agencies, and the public. |
|