Henley - A Historic Connection

Project Videos

The Latest on the Henley Project

Henley Update - October 17, 2013:

As of Thursday, October 17th, 2013 Henley Street Bridge is open to one lane of traffic in each direction.

Crews are working this week to finish paving and striping on the south side of the bridge. During the upcoming months, the contractor will continue to complete staining efforts and lighting installation.  Once these activities are completed, additional lanes will be able to be reopened. Modifications in the official detour will be made once the bridge is open.

The due date for total project completion is June 3, 2014.


WHAT WE'RE DOING
  • Contractor: Britton Bridge, LLC, Mt. Juliet, Tennessee
  • Amount: $24,696,969.47
  • Revised Contract Amount: $31,012,831.35
  • Henley Bridge Closures: Henley Bridge was closed to traffic on January 3, 2011
  • Henley Bridge will open to Traffic: February 28, 2014
  • Completion in Entirety: June 30, 2013
  • Project Completion in Entirety: June 3, 2014
  • Contract and Addendums: (pdf)  CNJ287, Addendum 1, Addendum 2, Addendum 3, Addendum 4