State Route 16 (U.S. 41-A)

Project Timeline

Transportation projects are developed in four phases: Planning and Environmental, Design, Right-of-Way and Construction. The following is a reflection of various aspects of these phases as they have occurred or will occur on the improvement of the three (3) sections of S.R. 16 under development:
   
Project Schedule for section from SR 64 to SR 276 (not currently programmed for construction)
Advanced Planning Report Completed May 25, 1996
Corridor/Design Public Meeting Completed Sept. 16, 2003
Public Meeting Completed Feb. 17, 2005
Approval of Final Environmental Document Completed Feb. 1, 2006
Conduct Right-of-Way Public Meeting Completed Sept. 12, 2006
Appraisals Completed March 29, 2009
Property Acquisitions and Relocations Completed February 15, 2011
   
Project Schedule for Section from SR 276 to west of Magnolia Lane. This section has been divided into two new segments in order to sustain funding for construction.
SR 276 to Rippy Ridge Road (programmed for construction in fiscal year 2014)
Property Acquisitions Completed March 27, 2009
Property Relocations Completed January 15, 2010
Award construction contract Forecast for late fall 2013
Rippy Ridge Road to west of Magnolia Lane
Roadway opened for traffic October 25, 2012
   
Project Schedule for section from Moore/Coffee Co. Line to N. Washington St.
Roadway opened for traffic March 9, 2007