| Total Project Length: Estimated Completion Date: Estimated Cost: Contract Awarded: Work Began |
3.925 miles December 31, 2014 $31.4 million December 10, 2010 February 10, 2011 |
| Materials Placed on Site to Date | |
| Cubic yards of dirt moved: |
107,916 |
| Tons Base Stone: | 3,188 |
| Tons of Asphalt: | 0 |
| Cubic Yards of Concrete: | 3,927 |
| Feet of new storm drain pipe installed: | 1,729 |
| Square feet of Sidewalk constructed: | 0 |
Contract Personnel on the Project
Construction Management and Inspection provided by Vaughn & Melton (Roadway) and Gresham Smith & Partners (Utilities)
| Prime Contractor: Sub-Contractors: |
APAC-Atlantic, Inc. Wooten & Associates (Construction Staking Bell & Associates, L.P. (Concrete Boxes and Retaining Walls) Dillard Smith (Electrical Lines) Progression Electric, Inc. (Lighting & Signalization) Tom Arnold Construction Company, Inc. (Under drain) Pipeline Construction Company, Inc. (Water & Gas Lines) Mayes Construction Company (Sewer Lines) Volunteer Highway Supply Co., Inc. (Striping) Tennessee Guardrail, Inc. (Guardrail) Shular Brackins & Sons, Inc. (Erosion Control Items) Linginfelter Landscaping, Inc. (Landscaping) Caution, Inc.(Permanent Signs) Superior Traffic Control (Construction Signs) Star Construction Company (Telephone) |
Project Videos
TDOT Chief Engineer Paul Degges discusses environmental processes
the department uses featuring the SR-62 project in Knoxville.

